3. On the following window, select

Enable

and click

Next

, then

OK

to exit. This will enable

the machine as a warm backup. This will complete the configuration and there is no need
to reboot the server.

4. When finished, launch ETV Backup using the desktop icon.

6. Test the Configuration

When you are finished configuring the IP addresses, click the

Run

icon in the navigation

footer. All backup profiles should run without errors and a window similar to the one shown
below will report a successful backup for each profile. If problems occur, for example if you
entered an invalid IP address, the window will report any failures. Correct the problems using
the information provided in the log window and try again.

T

To test the configuration:

1. Highlight the

MCS Warm Backup Group

and click

Run

.

2. Click

Continue Run

for each

Differences for profile: xxxxx

window and then

OK

.

3. If no errors occur, a window similar to the one shown below will be displayed.