Installation, Gas connection, Cut out size – Zanussi ZGL 62 ITX User Manual

Page 10

Advertising
background image

10

Rectangular cut-out size for hob

A)

End of shaft with nut

B)

Washer

C)

Elbow

FO 0814

Gas Connection

Connection to the gas supply should be with either rigid
or semi-rigid pipe, i.e. steel or copper.
The connection should be suitable for connecting to RC
1/2 (1/2 BSP male thread).
When the final connection has been made, it is essential
that a thorough leak test is carried out on the hob and
installation.
Ensure that the main connection pipe does not exert
any strain on the hob.

It is important to install the elbow correctly, with
the shoulder on the end of the thread, fitted to the
hob connecting pipe.
Failure to ensure the correct assembly will cause
leakage of gas.

Installation

IMPORTANT:

This hob must be installed by

a

competent person to the relevant Gas Standards.
Please, ensure that, once the hob is installed, it
is easily accessible for the engineer in the event
of a breakdown.

WHEN THE HOB IS FIRST INSTALLED

Once the hob has been installed, it is important to
remove any protective materials, which were put
on in the factory.
Any gas installation must be carried out by a
competent person.
The manufacturer will not accept liability, should
the above instructions or any of the other safety
instructions incorporated in this book be ignored.

On the end of the shaft, which includes the GJ 1/2"
threaded elbow, adjustment is fixed so that the washer
is fitted between the components as shown in the
diagram. Screw the parts together without using
excessive force.

FO 0264

Cut Out Size

The dimensions of the cut-out are given in the diagram.

Dimensions are given in mm.