6 Set up with the indicating and adjustment module

VEGAPULS 65 • HART and accumulator pack

40932-EN-121011

Product speed: slow filling and emptying

Vessel:

– Installations in the bottom section (bracers, heating spirals)

– High sockets 200 … 500 mm, also with large diameters

Process/measurement conditions:

– Condensation, buildup by movement

– Max. requirement on measurement accuracy from 95 %

Stirrer vessel (reactor):

Setup: all vessel sizes possible

Product speed:

– Fast to slow filling possible

– Vessel is very often filled and emptied

Vessel:

– Socket available

– Large agitator blades of metal

– Vortex breakers, heating spirals

Process/measurement conditions:

– Condensation, buildup by movement

– Strong spout generation

– Very agitated surface, foam generation

Dosing vessel:

Setup: all vessel sizes possible

Product speed:

– Fast filling and emptying

– Vessel is very often filled and emptied

Vessel: narrow installation situation

Process/measurement conditions:

– Condensation, buildup on the antenna

– Foam generation

Standpipe:

Product speed: very fast filling and emptying

Vessel:

– Vent hole

– Joins like flanges, weld joints

– Shifting of the running time in the tube

Process/measurement conditions:

– Condensation

– Buildup

Bypass:

Product speed:

– Fast up to slow filling with short up to long bypass tube possible

– Often the level is hold via a control facility

Vessel:

– Lateral outlets and inlets

– Joins like flanges, weld joints

– Shifting of the running time in the tube

Process/measurement conditions:

– Condensation

– Buildup