Geh-5673p2 – GE Industrial Solutions Spectra Series Power Panelboards AMC4GB and AMC6GB User Manual

Page 2

Advertising
background image

3. Prepare the breaker module (for two breakers only).

Before installing the breakers on the module, remove the

barriers and screws, as shown in Figure 4.

Figure 4. Preparing the breaker module for a two-breaker installation.

4. Install the circuit breaker(s). Place the Belleville washers

and hex-head screws into the line straps of the circuit

breaker, as shown in Figure 5. Position the ON side of the

breaker on the module, as shown in Figure 5. Align the

hex-head screws in the stud-post holes and tighten to 90–

110 in-lb. Fasten the OFF side of the breaker to the

mounting brackets with the round-head SEMS screws

and flat washers and tighten to 40–50 in-lb. Repeat the

procedure for a second breaker.

Figure 5. Installing the breaker on the module.

5. Install the center barrier. The center barrier must be

installed after the breaker has been secured to the

module. Slide the center barrier onto the breaker, as

shown in Figure 6 for a single breaker and in Figure 7 for

two breakers. Secure the center barrier with two thread-

cutting screws into each breaker and tighten to 10 in-lb.

Figure 8 shows a complete two-breaker installation.

Figure 6. Installing the center barrier with one breaker on the module.

Figure 7. Installing the center barrier with two breakers on the module.

Barrier

Mounting

Screw

Round-Head

SEMS Screw &

Flat Washer

Hex-Head Screw &

Belleville Washer

Mounting

Bracket

Stud Post

Center

Barrier

Thread-Cutting

Screws

Center

Barrier

Thread-Cutting

Screws

Advertising