Figure 8. Completed center barrier installation with two breakers.
6. Install the module. Fully retract the latches and hook
one side of the breaker module to the interior rail, as
shown in Figure 9. Release the latch. Pivot the module
onto the bus bars and engage the second latch.
Release the latch. Tighten the latch screws to 25 in-lb,
as shown in Figure 10.
Figure 9. Positioning the breaker module on the interior rail.
Figure 10. Securing the module to the interior.
7. Wire the circuits. Refer to the label on the circuit
breaker for the proper tightening torque.
8. Filler plate kits. Install filler plate kit AFP4SGC on the
module.
Attention – Procedure for Aluminum
Terminations
1. Strip the insulation, being careful to not nick the wire.
2. Clean the wire strands with a wire brush.
3. Thoroughly coat the stripped conductor with a
suitable antioxidant compound, such as ALNOX or
PENETROX A13.
4. Insert the conductor and tighten the connector screw
to the indicated torque on the rating label.
Latch
Latch
Screw
Latch
Screw