GE Industrial Solutions EntelliGuard G Command Closing Coil User Manual

Page 2

Advertising
background image

Figure 1. (A) Front Cover (B) ScrewRemoval (C) Handle

Rotation


4. Place the coil on the mechanism top plate and
assemble the connector marked as CCC from the

Command closing coil to the connector marked
as CCC in the Trip unit harness as shown in Fig. 2.

Figure 2. Plug Assembly


5. Tilt the coil forward and engage the front
hooks into the mechanism top support plate as
shown in the Fig. 3.

Figure 3. Coil Assembly

6. Tilt the device backwards until the rear hooks
engage in the slots on the mechanism top
support plate as shown in the Fig. 4.



Figure 4. Coil Assembly


7. After installing the closing coil on the
mechanism top plate, connect the input wire
assembly plug to the A9- A10-A11 locations
marked on the secondary disconnect as shown in

Fig. 5.

Figure 5. Close Coil Plug assembly


8. Ensure the plug is inserted properly by the snap
in the secondary disconnect.


9.

Place the ferrite from the coil assembly behind

the coil. Route the wire from the close coil to the

side of the PMU base for the connection with
Electrical close switch as shown in fig.6.