Figure 6. close coil wire routing, Figure 8. screw assembly, Figure 9. connector plug assembly – GE Industrial Solutions EntelliGuard G Command Closing Coil User Manual

Page 3: Figure 10. connector plug assembly

Advertising
background image

Figure 6. Close Coil wire routing

Installation of Electrical close switch:

10.

Slide the switch assembly over the

mechanism side sheet and locate in the two
locating holes as shown in Fig. 7.

Figure 7. EC switch assembly



11.

Assemble the screw with washer as shown in

Fig. 8. Tighten the screw to torque 1.2N-m (0.9 ft-

lbs).

Figure 8. Screw assembly

12. Plug the connector from the EC switch

assembly to the connector from the command
closing coil beside the PMU base as shown in
Fig 9.

Figure 9. Connector plug assembly

Installation of Push button on the fascia:

13. Remove the existing dummy button by

removing the screw as shown in fig 10.

Dummy button
Screw

Figure 10. Connector plug assembly