GE Industrial Solutions Power-Vac Metal Clad Switchgear; Section 3 User Manual

Page 15

Advertising
background image

54

Fig – A(1)-6

Location of tape

Fig A(1)-7

Typical Bus compartment with polyester glass inter-unit bus support

Step – 6 Align switchgear stacks

a) Gently align the next stack on the left with this stack taking care not to damage

the porcelain bus supports.

b) When the eight bus support holes ( four holes for polyester glass bus supports )

are aligned, replace the bus support assembly against the side sheet and use the ¼
- 20 hardware to fasten the bus supports and the two side-sheets together as shown
in Fig A(1)-8

c) A black rubber gasket is provided to cover the edge of the side sheets around the

perimeter of the bus pass-through cutout for 15kV gear. It should be ensured that
this gasket is in place.