Fig – A(1)-9

Shows rubber cushion inserted over bus

Step 8, Finishing up

a) Re-assemble the boots that were removed in step 4.
b) Remove tape applied in step 5a ( for porcelain only )
c) Ensure that no tools or other material is left behind in the bus compartment
d) Re-assemble the vertical mid-barriers and the horizontal pan that were removed

in steps 1 to 3

e) Before energizing the switchgear conduct Insulation resistance (Megger) and HV

Hipot tests ( optional ) as described in the instruction books.