Installation

7

insTallaTion

Only for control head without pre-assembled process valve.

7.1 safety instructions

Danger!

risk of injury from high pressure in the equipment/device.

▶ Before working on equipment or device, switch off the pressure

and deaerate/drain lines.

risk of electric shock.

▶ Before working on equipment or device, switch off the power

supply and secure to prevent reactivation.

▶ Observe applicable accident prevention and safety regulations

for electrical equipment.

Warning!

risk of injury from improper installation.

▶ Installation may be carried out by authorized technicians only

and with the appropriate tools.

risk of injury from unintentional activation of the system and
an uncontrolled restart.

▶ Secure system from unintentional activation.

▶ Following assembly, ensure a controlled restart.

7.2 installation of the control head on

process valves of series 21xx

Procedure:

When the control head is being installed, the collets of the
pilot air ports must not be fitted to the actuator.

note!

damaged printed circuit board or malfunction.

▶ Ensure that the puck is situated flat on the guide rail.

Align the puck and the control head until
1. the puck can be inserted into the guide rail of the

control head (see “Fig. 4”) and

2. the connection pieces of the control head can be inserted

into the pilot air ports of the actuator (see also “Fig. 5”).

Guide rail

Puck

Connection
pieces

Fig. 4:

Aligning the puck