Installation, Important – Poweramp TPR SERIES User Manual

Page 13

Advertising
background image

11

4111-0035 — Feb 2012
Aug 2012

INSTALLATION

Post safety warnings and barricade the work area at
dock level and ground level to prevent unauthorized
use of the dock leveler before installation has been
completed.

Failure to follow the installation instructions can
result in damage to dock leveler, the facilities, and/
or serious personal injury or death.

IMPORTANT

DO NOT connect the dock leveler electrical wiring
and ground connections until all welding has been
completed.

DO NOT ground welding equipment to any hydraulic
or electrical components of the dock leveler. Always
ground welding equipment to the dock leveler frame,
NEVER to the platform.

Failure to follow these instructions may damage the
motor, hoist cylinder, wiring, and/or control panel.

11

WELDING INSTALLATION INSTRUCTIONS

If the installation being worked on is a retrofit
or replacement situation, the following electrical

connections must be disconnected prior to welding:

LOCKOUT/TAGOUT the power at the fused
disconnect, then remove the motor and limit switch
connections from the control harness located in the
outside junction box. Once all welding has been
completed, reconnect all the wires.

NOTES:

1. NEVER install the TPR vehicle restraint directly

onto concrete block or brick dock face.

2. When welding the TPR vehicle restraint,

disconnect power and ground leads to leveler.

3. Due to actual conditions, total mounting height

may be different.

4. Plug weld all holes that are in contact with the

embedded mounting plate. All fifteen (15) holes
must be either plug welded or anchored.

5. Shims must be the full length of the roller track

mounting plate. Minimum electrode must be 1/8"
7018 or better.