Introduction

The following instructions are given for the
guidance of the operator in the use of
Fulton Electric Steam Boilers. Before
operating your Fulton Electric Steam Boiler:

STOP!

Make sure you have read and followed
all previous safety information.

NOTE

Check with local authorities where
approval for start-up is required. In
some localities, final inspection of
services may be required.

CAUTION

In general, ensure that the boiler area is
in conformance with established boiler
room requirements. Review national
and local codes.

Starting the Boiler

Do not attempt to start the boiler until all of
this section has been read. Carry out the
following procedure on the initial start up of
the boiler and on every subsequent
occasion when restarting the boiler after a
shut down.

1. Close blow-off valve.

2. Close water gauge drain valve.

3. Open main steam stop valve at the top of

the boiler.

4. Open water feed valve on boiler.

5. Open valves on makeup water line to

return if return system is used.

6. Place feedwater pump fused switch in

the “on” position. The water pump will
continue to operate until the water has
reached the proper level in the boiler.
This level is at about the center of the
water gauge glass.

7. To check proper boiler control operation

and pressure control settings, you may
choose to close the steam supply valve
on initial start up. This will enable you to
observe the complete boiler operation
without heating the complete system.
The fused switch that controls the feed
water pump should be kept in the “on”
position at all times during the boiler
operation as well as during the non-
operating period of the boiler. This
should be turned off only when repairs
or adjustments are to be accomplished.

8. Turn the switch on the boiler to the “on”

position. The white light will light
indicating that the electrical circuit for the
boiler has been energized and that all
controls are working properly.

20