C A U T I O N

!

> Do not depress the manual brake button

if turbine speed is zero. This will cause the

turbine shaft to rotate in reverse. This will

cause damage to the turbine assembly.

The applicator is now ready for placement into the

production environment once the last few steps

have been completed.

1. Turn bearing air regulator to zero pressure.

2. Release all pressures from the system includ-

ing the pressure in the pressure pot.

3. Press the control power off button on the front

panel.

4. Remove the applicator from the mounting plate

using the proper spanner wrench.

3. Turn the fluid selector switch to the “Air” posi-

tion. (Refer back to Figure 7.)

4. Trigger the dump Paint #1 and Paint #2 toggle

switch in the fluid enable section of the panel.

(Refer back to Figure 9.)

5. Trigger the Paint #1 and the Paint #2 toggle

switches to blow out any excess water. There

are (2) dump solenoids on this dual paint as-

sembly. Each paint line has its own dump line.

(Refer back to Figure 10.) Turn off the dump

switches.

6. After 3 to 4 minutes of purging with air, inspect

visually to determine if all the fluid has been

pushed out of the coiled lines

7. Trigger solvent in to the “On” position in the

fluid enable section. Trigger the (2) paint lines

(Paint #1, Paint #2, and solvent), to purge any

residual material in these areas. This material

will exit from the bell. All three may be trig-

gered at one time. Allow air to blow through

the lines for an additional 30 to 40 seconds.

8. Turn off all the triggers that are on. Use the

manual brake to stop the turbine.