9 Commissioning

Local standards and specification requirements must be adhered to. A typical commissioning procedure
might entail the following steps:

Check installation against

design documentation

T

Set detector configuration DIL

switches as required

T

Disconnect detector from fire

panel if required

T

Power up detector and wait for

15 minute FastLearn cycle to

finish (steady “OK” LED when

complete)

T

Check/test connections to main

Fire Detection and Alarm

System

T

Smoke test: check maximum

transport time is less than 120s,

verify sampling hole sensitivities
as required. Verify that smoke is

not prevented from reaching

sampling holes, e.g. by strong

air currents such as might be

caused by air-conditioning units

T

Reconnect detector to fire panel

if

required

T

Complete test records; record

settings and results for

reference by maintenance

engineers