OVEN SERVICE PROCEDURES

Multi-Valve Adjustment Procedure

Check Incoming Pressure:

Loosen screw 1 full turn counter clockwise (Figure 1)

Hook up Manometer to this test port

Turn main switch to the on position

Document incoming pressure on startup checklist. (If new installation)

Figure 1

Turn Main switch to the off position

Disconnect Manometer

Tighten screw clockwise until snug (Figure 2)