Installing the fc16-64, Before you begin, Esd precautions – Brocade FC16-64 Port Blade QuickStart Guide (Supporting DCX 8510-4 and DCX 8510-8 with Fabric OS 7.3.0 and above) User Manual

Page 9: Time required for installation tasks, Items required

Advertising
background image

Installing the FC16-64

Before you begin............................................................................................................... 7

ESD precautions............................................................................................................... 7

Time required for installation tasks................................................................................... 7

Items required................................................................................................................... 7

Installing the blade in the chassis..................................................................................... 8

Attaching cables to the blade............................................................................................ 9

Bundling and routing cables............................................................................................10

Attaching cables to the patch panels.............................................................................. 12

Before you begin

Be sure to establish a naming or numbering scheme before you begin attaching cables. Each cable
should have a unique designation and should be labeled accordingly. You should also record this
information separately for future reference and troubleshooting. If you are using break-out cables,
remember to label appropriately that you know which ends are being connected. Refer to the serial
numbers on the break-out side of the cables for proper identification of individual channels or ports.

ESD precautions

The Brocade DCX Backbone series contains ESD-sensitive field-replaceable units (FRUs). When
working with any FRU, use correct electrostatic discharge (ESD) procedures.

Wear a wrist grounding strap connected to chassis ground or a bench ground.

Store ESD-sensitive components in antistatic packaging.

Time required for installation tasks

Installing a single FC16-64 in a chassis should take less than five minutes.

Refer to the documentation accompanying any patch panels for the approximate time to install and
pre-cable the panels.

Attaching cables, bundling and routing them, and attaching the cables to the patch panel for one
FC16-64 should take approximately 40 minutes, depending on experience and the ability to work
with cable connections.

Items required

You should have the following items before you start installing FC16-64 port blade:

FC16-64 Port Blade QuickStart Guide

7

53-1003197-01