Positioning

The installation position should be selected with the following points in mind:

Position on a stable and even base, levelled to ensure that the compressor
operates correctly.

Levelling should be to +/- 5mm.

Where vibration transmission to the building structure is possible, fit pad anti-
vibration mounts.

Observe airflow and maintenance clearances.

Pipework and electrical connections are readily accessible.

Where multiple units are installed, due care should be taken to avoid the
discharge air from each unit adversely affecting other units in the vicinity.

Within a side enclosed installation, the fan MUST be higher than the
enclosing structure.

Ensure there are no obstructions directly above the fans.

Allow free space above the fans to prevent air recirculation.

CAUTION

Prior to connecting services, ensure that the equipment is installed and
completely level.

REAR

092 Models

LEF

T

RIG

HT

(1) Airflow clearance minimum 300 (mm),
(2) Maintenance clearance minimum:

Single unit minimum 750mm

FRONT

REAR

122 Models

LEF

T

RIG

HT

(1) Airflow clearance minimum 300 (mm),
(2) Maintenance clearance minimum:

Single unit minimum 750mm

FRONT