InfraStruXure Site Planning, Installation, Start-Up

9

Basic Installation Procedure

This section provides the basic steps that you need to perform when installing InfraStruXure power

and rack components. Follow the references provided with each step for detailed instructions.

1. Unpack the components according to the unpacking instructions included on the outside of the

packaging or in the installation manual included with the component.

2. Determine the correct placement of your system components by studying your APC

InfraStruXure configure-to-order (CTO) report. Move the InfraStruXure PDU and enclosures to

their final location.

3. Join adjacent NetShelter enclosures.

4. Bolt enclosures to the floor.

5. Ensure total power off.

Do not begin installing your InfraStruXure system without an APC Field Service

Engineer present.

Make sure that all boxes and packaging are empty before discarding them.

If installing InfraStruXure on a raised floor, make sure that the raised-

floor structure has a kg/m

2

rating that will support the full weight of the

InfraStruXure installation. See “Weight Considerations” on page 6.

See also

For instructions on joining adjacent NetShelter VX Seismic Enclosures, see the

installation manual included with your enclosures.

See page 11 for detailed instructions.

See page 12 for detailed instructions.