Test schedule, Test duration – American Power Conversion 250 A User Manual

Page 50

Advertising
background image

Testing

40

InfraStruXure Power Generation System

Test Schedule

Test Duration

Use this menu to schedule a test in the future.

Define Schedule

Set the test schedule by changing the following parameters:

Gen Start: Choose when to perform a

generator start test. Choices are Never,
Monthly, Weekly, or Daily.

Day: The choices for Day depend on the

choice made for Gen Start:

If you chose a GenStart of Never: The Day is not configurable.

If you chose a GenStart of Monthly: Choose to perform the test on the 1st, 2nd,
3rd, or 4th week of the month on a specific day of the week.

If you chose a GenStart of Weekly: Choose to perform the test on any day of the
week.

If you chose a GenStart of Daily: Choose to perform the test Everyday, on
Weekdays (Monday through Friday), or on Weekends (Saturday and Sunday).

Time: Set the time of day the test will run. The time is set on a 24-hour clock.

Load Test: Choose to test the generator with the data center load applied. Choose

to perform the load test By Month, Monthly, Never, or All.

Choosing Monthly for the Load Test ensures this test will take place on the first
occurrence of the Gen Start Test.

Next Test

Lists the date and time of the next test.

Gen Start: Monthly
Day: 1st Monday
Time: 14:30
Load Test: Monthly

The following items are available on this menu:

Warm Up

Set the amount of time, in seconds (up to 999), that the generator will warm up
during a test.

Loaded

If the Load Test option is selected, set the amount of time, in minutes (up to 999),
that the generator will run with the data center load applied.

Cooldown

Set the amount of time, in seconds (up to 999), that the generator will cool down
after the test.