17

INSTALLATION

OPTIONAL ADD IN BOILERS

Aarrow Ecoburn Wood and Multifuel stoves offer
the option of a slab boiler, which occupies the posi-
tion of the rear firebox liner panels.

Fitting:
•Remove the fuel retainering bars, rear firebox liner

panels and throat plate.

•Knock out the blanking discs in the back

plate corresponding to the terminals on the
boiler.

•Introduce the boiler to the appliance

through the main fire door and locate the
terminal pipes through the back plate holes
and seal around boiler terminals with fire
cement.

•Engage locking nuts to the thread of the

terminals and tighten to secure the boiler in
position, ready for connection to flow and
return pipes.

•Replace throat plate and the fuel retainering bars.

Note: On boilers the terminal which is
approximately flush with the edge of the boiler
and marked "TOP" must be fitted uppermost, to
prevent "Kettling".

WATER CONNECTIONS

Heating systems

The size of the heating system which can be run,
will depend on the output rating of the appliance. It
will be necessary to work out heat loss calculations
for the system proposed in order to establish the
kW/hr rating. An appliance that will meet this
figure can then be chosen; (for boiler outputs please
refer to the brochure).

The constructional requirements of installing and
connecting the appliance also need to be taken into
account when selecting. Design and calculations
for individual heating systems should be carried out
by a qualified heating engineer. In many cases your

supplier will be able to offer advice and assistance.

Direct Systems

Stainless steel boilers, either factory fitted or
retro-fitted as add-in boilers enable connection to
direct systems to be made without the need to
change the cylinder or to fit an expansion tank. This
applies to domestic water supply only and should
not be done when in an area with soft water.
If
radiators are used then an indirect system must be
utilised.

To connect the cylinder use 28mm copper pipes.
Ensure that the pipes rise continuously to the
cylinder.

Ensure that the runs are not too long, i.e. 20ft
maximum each for flow and return. Install the
cylinder above the level of the fire, and as close to
it as possible. (the higher the cylinder the faster the
circulation). Ensure that no valves are present in the
circulating pipes.

Indirect Systems- The Domestic Hot Water
Circuit

In addition to providing hot water the primary
circuit is essential in providing a "heat leak" to
absorb excessive heat produced in the event of the
circulation pump shutting down.
Heat is produced in varying quantities while the
fire is alight and care must be taken to ensure that
effective circulation can occur around the primary
circuit to carry heat away and thus stop boiling. The
output of any radiator installed as a "heat leak"
should not be less than 10% of the rated output of
the appliance. The radiator should not be fitted
with a control valve.
The cylinder must be of the indirect type with a
minimum capacity of 110 litres, conforming to
BS 1566 part 1.

Advertising