PlACING A REGUlATOR IN SERVICE (Continued)

CHECkING FOR PROPER OPERATION

Refer to the control unit instruction manual and use

the following procedure to check for proper regulator

operation. (Switch designations referenced below are

applicable to the HI/ICMI control.)

1. Set the MOTOR CONTROL AUTO/MANUAL switch to

“MANUAL”.

2. Holding the the MOTOR CONTROL RAISE/LOWER

switch in the “LOWER” position, run the regulator in

the lower direction until the control panel LOW BAND

indicator illuminates.

3. Set the MOTOR CONTROL AUTO/MANUAL switch to

the “AUTO” position. After a time delay, the regulator

will automatically return to an IN-BAND condition. The

control panel IN-BAND indicator will illuminate.

4. Set the MOTOR CONTROL AUTO/MANUAL switch to

the “MANUAL” position.

5. Holding the MOTOR CONTROL RAISE/LOWER switch

in the “RAISE” position, run the regulator in the raise

direction until the control panel HIGH BAND indicator

illuminates.

6. Set the MOTOR CONTROL AUTO/MANUAL switch to

the “AUTO” position, After a time delay, the regulator

will automatically return to an IN-BAND condition. The

control panel IN-BAND indicator will illuminate.