Install the valve STOP.
Lightly coat the valve
STOP stud thread with
Loctite #242 or equiva-
lent, then install the
valve STOP 1/4” nut.

Using a criss-cross pat-
tern, tighten and torque
the three 1/4”-20 screws
and valve STOP nut to
20 ft.-lbs. (27 N-m).

Tighten and torque the
handle hex screw (1/4”-
20) to 10 in.-lbs.
(14 N-m).

7.

Install the valve ball by
carefully sliding it into
the valve body opening
(from either side).
(See Figure 6-6:
“Installing the Valve
Ball.”)

If the valve ball
includes a balance
hole, the balance hole
must face the INLET
side of the valve.