VALLEY PANEL AND TRIM INSTALLATION

Details are subject to change without prior notice.

1. Start at the low end, trim and place the valley flashing. The valley end should overhang the eave trim 1”.

2. If there is an end lap required in the valley pieces, caulk and lap at least 8”.

3. Use wafer head screws on 5’ centers to secure the valley in place along the outside edge.

4. Hem the edges of the valley over the eave trim, after trimming the center “V” back 1” to align with the

edge of the eave. Leave a tab to bend and cover the exposed opening of the center “V”.

5. Place butyl tape on the upper surface of the valley 6” up slope from the “V” of the valley trim,

before applying intersecting panels.

6. Field cut the panels that intersect the valley holding the end of the panel 4” back from the “V” of the

valley trim and parallel to the “V” of the valley.

7. Attach panel at valley using eave screw requirements for panel being installed.

NOTE: Alternate trim profiles are acceptable using the screw pattern shown.

NOTE: To comply with Texas

Windstorm Certification Testing,

#12x11 SDT Type A screws must

be used in place of the #9

Woodgrip screws.