STANDARD RIDGE ROLL and HIP INSTALLATION

1. Lay a piece of the #0221 ridge roll or hip in position, making sure it is centered and in the correct position.

(Refer to step #7 for end capping instructions)

2. Temporarily fasten the ridge roll in place at one end with a lap screw, positioning the screw through

the hem of the ridge roll, centered on the corrugation.

3. Position the corrugated closure on the sheet.

4. Attach with (1) lap screw, centered on the corrugation, 12” O.C., through the hem of the ridge roll and through

the corrugated closure, into the panel. Care must be taken not to over-tighten the screws, as this will distort the
trim and closures. The screw hole can be pre-drilled, if desired.

5. Continue installing the closures the entire length of the ridge or hip. Remove the temporary fastener, insert the

closure, and fasten through the existing hole as in step 4.

6. All end laps should be at least 4”. Secure to the overlapped piece with caulk and stitch screws.

7. Cap the end of all ridge roll and hips by cutting and folding ends. Capping is usually easier to do before the piece is

installed. If done after installation, be sure and leave 6” of the ridge roll or hip overhanging the peak or corner to
allow enough material for cuts and folds.

NOTE: Alternate trim profiles are acceptable using the screw pattern shown.