INITIAL SET-UP (TB3/TB3-LP ONLY)

CAUTION - The brewer must be disconnected from the power source throughout the initial set-up, except when

specified in the instructions.

1. Remove the top lid from the brewer.

2. Rotate the control thermostat knob fully counterclockwise to the "OFF" position and replace the top lid.

3. Set the delay dial on the timer at three minutes and set the dilution dial at three to four minutes.

4. Remove the metal discharge tip from the funnel to speed up the set-up procedure. Insert the empty funnel

into the funnel rails.

5. Place an empty dispenser on the brewer base. Be sure the funnel discharge is directly above the hole in the

dispenser top lid.

6. Plug in the brewer and place the ON/OFF switch in the "ON" position. Momentarily press the start switch.

Water will flow into the tank and will shut off after three minutes. Press the start switch again. During the

second period, the tank will fill to its capacity and the excess will flow from the funnel into the dispenser.

7. Place the ON/OFF switch in the "OFF" position.

8. Disconnect the brewer from the power source and remove the top lid.

9. Rotate the control thermostat knob fully clockwise to the "ON" position and replace the top lid.

10. Plug in the brewer and wait for the water in the tank to heat to the proper temperature (approximately 20

minutes). Some water will drip from the funnel during this time; this is due to expansion and should not

occur thereafter.

11. Place the ON/OFF switch in the "ON" position and press the start switch. Empty the dispenser after water has

stopped flowing from the funnel.

12. Allow the water in the tank to reheat to the proper temperature.

13. Place the ON/OFF switch in the "ON" position and press the start switch.

14. Place the ON/OFF switch in the "OFF" position immediately after water stops flowing from the funnel. Check

the water volume in the dispenser. It should be seventy-six ounces.

15. If not, adjust the digital timer as required. See Adjusting Brew Volumes on page 5, and measure another

concentrate cycle.

16. Repeat steps 12-15 until the proper water volume is achieved.

17. Unplug the brewer and remove the top lid.

18. Set the delay dial on the timer at three minutes and empty the dispenser.

19. Place the ON/OFF switch in the "ON" position, momentarily press the start switch, and allow both the con-

centrate and dilution cycles to occur.

20. When all water stops flowing, check the water volume in the dispenser. It should be 396 ounces.

21. If not, unplug the brewer and remove the top lid.

22. Adjust the dilution dial on the timer as required. Replace the top lid, plug in the brewer, start, and measure

another brew cycle.

23. Repeat steps 19-22 until the proper water volume is achieved.

24. Return the delay dial on the timer to eight minutes. Replace the top lid and plug in the brewer.

25. Reinstall the metal discharge tip into the funnel.

26. Load the funnel with a BUNN® paper filter and approximately four ounces of loose tea leaves.

27. Place the ON/OFF switch in the "ON" position, momentarily press the start switch, and allow both the con-

centrate and dilution cycles to occur. Observe the funnel discharge and the dilution streams near the end of

the brew cycle. The dilution stream should stop approximately thirty seconds after the funnel discharge has

stopped.

28. If not, unplug the brewer and remove the top lid.

29. Adjust the delay dial on the timer as required. Replace the top lid and plug in the brewer.

30. Repeat steps 26-29 until the proper dilution timing is achieved.