Process Sequence Example

MTS MultiPurpose TestWare®

Working with MPT Processes

93

Process Sequence Example

Assume when you start your test you want the program to ramp up, cycle for
some time, ramp down, and then end.

You would sequence your processes to run in the following order:

The “Ramp Up” Segment process should start when the procedure starts.

The “Cycle” Cyclic process should start when the “Ramp Up” process is
done.

The “Ramp Down” Segment process should start when the “Cycle” Cyclic
process is done.

The Procedure should end when the “Ramp Down” Segment process is
done.

The following procedure table illustrates this: