INSTALLATION PROCEDURE

I. Charger

Inspection

1. Upon receipt of the Element charger, verify that the shipping information (packing list)

matches the charger rating (label on the side of the charger).

2.

Upon receipt of the Element charger, ensure that there is no physical damage to the

chassis, the LCD/keypad, the E-Stop/Disconnect switches, or the AC/DC cables. If you

notice any damage, inform the shipping carrier and/or GNB Industrial Power.
Do not install or operate the unit if it has received a sharp blow, been dropped or

otherwise damaged.

II.

Charger Physical Installation
1.

Ensure that the charging area is well ventilated, dry, and adequately clean.

2.

Do not restrict airflow to the bottom air filter or top cover. Leave at least 1 ft spacing

between the sides of the charger and any adjacent walls or barriers and 2 ft spacing

between the bottom of the charger (air filter) and the floor / any mounting brackets.

3.

Use a cardboard sheet as a template to mark the locations for the hardware on the wall.

4.

Drill and install the hardware needed to mount the charger on the wall.

5.

Lift the charger and mount it on the wall using the installed hardware (Figure 1).

Use ¼-20 hardware with lock washers to secure the charger to wall.

Figure 1: Charger installation