2.

Medical air, instrument air, medical vacuum and WAGD controls are to be wired in accordance

with

NEC.

3.

MGEM will include with submittals an affidavit attesting to compliance with all relevant paragraphs

of NFPA 99 most recent edition including (d) below.

4.

MGEM personnel assembling medical air, instrument air, vacuum and WAGD plant shall meet the

latest edition of NFPA 99 section titled “Qualification of Installers” and hold medical gas

endorsements as under ASSE 6010.

5.

The Contractor shall furnish documentation attesting that all installed piping materials were

purchased cleaned and complied with the requirements of NFPA 99 5.1.10.1 and 5.1.10.2.

6.

The Contractor shall furnish copies of ASSE 6010 qualifications for all workers installing medical

gas

piping.

B.

Installation and Start-up

1.

The MGEM will provide authorized representatives to review installation and perform initial start up

of

system.

C. Warranty

1.

Warranty will be expressly complete, include all components of the system and be the responsibility

of the MGEM for record only. Warranties limiting the responsibility of the MGEM for any system

component or which pass through the MGEM to another manufacturer are not acceptable.

2.

All source medical gas components shall be warranted by the MGEM of record for a minimum of 30

months from date of shipment.

3.

Warranties shall include on site repairs including travel, labour and parts.

4.

Shipping and installation costs after the first 12 months will be borne by the customer.

D. Verification


1.

Medical Gas Contractor shall deliver to the owner a complete system certification.

PART 2 - PRODUCTS

QUALIFICATION OF MANUFACTURER(S)

A. The manufacturer shall supply all of the medical gas systems and equipments to include outlets, valves and
gauges,

valve boxes, alarm panels, manifolds, medical air, instrument air, vacuum and WAGD sources.

B.

The MGEM shall have a product specialist available to periodically check with the contractor during

installation of the pipeline systems equipment. MGEM shall provide service support to the hospital after

turnover. Demonstrate factory trained service technician is available within 250 miles of facility.

C.

Approved MGEM: Piping Systems Components and Medical Gas Alarms

1. Amico Corporation.

2. Alternate by _____________ with pre-approval.

12