ENGLISH INSTRUCTIONS

Installation Instructions

1. Consult local codes for specific installation

requirements and restrictions applicable to

your area. It is recommended that system

supply pressure be at least 20psi (138 kPa).

2. These instructions apply to Series

870V/876V, and LF870V/LF876V/876VST

sizes 2

1

2

" to 10" (65-250mm) only. The

valves may be installed only in the orienta-

tion/flow direction as shown. All 870V/876V

and LF870/LF876V/876VST assemblies are

shipped in the horizontal installation orien-

tation only. The gate valves may be rotated

as permitted by the flange bolt pattern.

3. The valve assembly must be installed

where it is accessible for periodic testing

and maintenance. Clearances shown in the

installation views apply to exterior, interior

and pit/vault installations and are only rec-

ommendations. These minimums do not

apply to removable protective enclosures.

Refer to local codes for actual requirements

in your area.

4. PRIOR TO INSTALLING THE VALVE INTO

THE LINE, FLUSH THE SUPPLY LINE OF

ALL FOREIGN MATERIAL. Failure to flush

the supply line may cause the check valves

to become fouled and require disassembly

and cleaning.

5. Lift the assembly by connecting lift

hooks to the lift rings cast into the valve

body. DO NOT LIFT THE ASSEMBLY

BY CONNECTING TO THE GATE VALVE

HANDWHEELS OR STEMS. The use of the

optional valve setters (horizontal units only)

provides for a rigid connection to the sup-

ply line (with the correct centerline) without

the need for concrete thrust blocks.

6. For vertical installation, loosen bolts on

the groove coupling just enough to allow

rotation of the outlet check. Rotate outlet

check 180º. Ensure that the vertical support

adapter is in place (valve is shipped with

adapter banded in place) and install pipe

support (pipe support to be furnished by

the customer and shall fit same size pipe

as the valve being installed, except 2

1

2

"

(65mm) valves will use a 3" pipe support).

NOTICE

THE VALVE BODY AND PIPE SUPPORT ARE

INTENDED TO SUPPORT THE WEIGHT OF

THE SECOND CHECK VALVE AND OUTLET

GATE VALVE ONLY. THE PIPING ABOVE THE

OUTLET GATE VALVE MUST BE SUPPORTED

INDEPENDENTLY. Retighten bolts of groove

coupling. Rotate outlet gate valve as desired

– required.
6a. For vertical installation of the DCDA, first

remove formed tube from bypass piping,

then follow instructions outlined in No. 6

above. When this has been completed,

rotate the compression fitting elbow 180º

and reinstall the tube, rotating the pipe tee

now at the bottom of the outlet check to

align with tube.

7. After installation SLOWLY fill the assembly

with water and bleed air from the body

using the # 3 and # 4 test cocks. Test the

valve assembly to ensure correct operation.

You are required to consult the local building and plumbing codes prior to installa-

tion. If the information in this manual is not consistent with local building or plumb-

ing codes, the local codes should be followed. Inquire with governing authorities for

additional local requirements.

WARNING

!

Need for Periodic Inspection/Maintenance: This product must be tested periodically

in compliance with local codes, but at least once per year or more as service conditions

warrant. All products must be retested once maintenance has been performed. Corrosive

water conditions and/or unauthorized adjustments or repair could render the product

ineffective for the service intended. Regular checking and cleaning of the product’s internal

components helps assure maximum life and proper product function.

WARNING

!

WARNING

!

Read this Manual BEFORE using this equipment.
Failure to read and follow all safety and use information can result in death,

serious personal injury, property damage, or damage to the equipment.
Keep this Manual for future reference.

Advertising