S U N C O N T R O L - I N S T A L L A T I O N M A N U A L

CW-250 ASSEMBLY

Attach anchor using

(6) 5/16" X 1" hex head

bolts & washers

CW-2058

CW-2059

CW-3

CW-2

Install CW-2059 anchor with

(6) 5/16" bolts, washers &

locknuts prior to installing glass.

FIGURE 3

FS-322

1.2 Assembly

3) Hardware required for attachment of standard anchor (CW-2058) will be contained in the

hardware package, (part. no.12845). This package contains (1) one CW-2059 cover plate,

(6) six 5/16"- 18 x 1" stainless steel hex head bolts, nuts and washers and (4) 3/8"-16 x 1-1/4"

stainless steel hex head bolts, nuts and washers.

4) Attach anchor to mullion by first hooking into tongue of mullion. The 5/16" nuts will next in the

side of the anchor and allow the bolt to be inserted through the stem and anchor and

tightened. Repeat for each of the 6 bolts. See FIGURE 3 (Size and quantity of bolts may

vary based on project requirements, consult engineer for specific job applications).

5) Once system is glazed, install section of CW-17 gasket onto CW-2059 cover plate and install

plate over anchor attaching to mullion using (2) two FS-322 (#12-14 x 1" HWH Drill-Flex

fasteners).

Note: Due to reduced clearance for attachment of anchors, special care must be taken when

installing glass.

Notes:

1) Assembly package part no. 12845 required for

installation.

2) Anchor must be installed prior to glazing.

3) Glass clearance at anchor is reduced to 3/16", so

care should be exercised during installation of glass.