2 installing gas supply manometer – AERCO Innovation (G-14-2265 and above) User Manual

Page 54

Advertising
background image

Innovation Water Heaters Installation, Operation & Maintenance Manual

CHAPTER 4 – INITIAL START-UP

Page 54 of

206

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913

OMM-0078_0L

PRI: 11/25/2014

Phone: 800-526-0288

GF-128

• Digital Combustion Analyzer: Oxygen accuracy to ± 0.4%; Carbon Monoxide (CO) and

Nitrogen Oxide (NOx) resolution to 1PPM.

• 16 inch W.C. manometer or equivalent gauge and plastic tubing.
• Multimeter (Capable of measuring 0 – 10 µA)
• 1/8 inch NPT-to-barbed fittings for use with gas supply manometer or gauge.
• Small and large flat blade screwdrivers.
• Tube of silicone adhesive

4.2.2 Installing Gas Supply Manometer

The gas supply manometer is installed in the gas train as follows:

Installing Gas Supply Manometer

1.

Close the main manual gas supply shut-off valve upstream of the unit.

2.

Remove the front door and left side panels from the heater to access the gas train
components.

3.

Remove the 1/4 inch NPT pipe plug from the leak detection ball valve on the downstream
side of the Safety Shut Off Valve (SSOV) as shown in Figure 4-1.

4.

Install a NPT-to-barbed fitting into the tapped plug port.

5.

Attach one end of the plastic tubing to the barbed fitting and the other end to the 16 inch
W.C. manometer.

Figure 4-1. 1/4 Inch Gas Plug Location (INN600-1060 Gas Train Shown)

MANUAL

SHUTOFF

VALVE

SSOV

1/4" NPT PLUG

(Install manometer here)

LEAK DETECTION

BALL VALVE

TO
AIR/FUEL

LOW GAS
PRESSURE
SWITCH

HIGH GAS

PRESSURE

Advertising