KERN & SOHN IEX 100K-1MEU Safety User Manual

Page 11

Advertising
background image

IEX-BA-e-1410

11

8

Technical surveys

Technical inspection of a scale operating in explosive area has to be

carried out by a trained personnel at least once every three months.


Each technical inspection should cover:

Grounding quality: the quality of fastening to the housing and the resistance of

connection -

max. 100Ω,

Quality of the connection between the platform and the indicator (pliant steel pipe

connecting the two subassemblies).

The damage and loosing one of connection is inadmissible.

Electrical connection between the housing and the platform - max. resistance

between the weight pan (put on) and the housing should be lower than 100Ω.

Stability and levelling of the scale.


Advertising
This manual is related to the following products: