Form I-ADF, Page 16

Thread

bleed line

fitting (hose

barb) into

the adapter;

attach a

1/4" hose.

FIGURE 15 - Bleed Line Fitting

Bleed Line Connection (Does not apply to module with optional timed meter-

ing system.) - Shipped in the evaporative cooling module bottom pan, find a

1/4" I.D. x 1/2" N.P.T. nylon bleed line fitting (hose barb). Thread the fitting into

the female adapter located opposite the pump/inlet side of the water distribu-

tion line. The hose barb will protrude from the side of the cabinet (

FIGURE

15). Attach a 1/4" I.D. hose to the barb and run the hose to the nearest drain.

Discharging a quantity of water by "bleed off" will limit the concentration of

undesirable minerals in the water being circulated through the cooling module.

Minerals buildup because evaporation only releases "pure water vapor" caus-

ing the concentration of contaminants in the water to increase as the evapora-

tion process continues to occur. The minerals accumulate on the media, in the

water lines, on the pump, and in the reservoir. Adequate bleed off is important

to maintaining an efficiently operating evaporative cooling system.

Supply and Drain Water Connections (cont'd)

Evaporative

Cooling

Module

Float valve inlet water connection

(1/4” compression) or inlet water

connection to solenoid valve

for metering system (1/2” male fitting)

Overflow fitting -

3/4” garden hose

thread tapped with

1/2” female NPT

Drain fitting - 3/4”

garden hose thread

tapped with

1/2” female NPT

2-way solenoid valve

(normally open)

3-way

solenoid

valve

To drain

Pressure regulator

(10 psi max)

Service valve

Roof Line

= Field supplied
= Field-installed water piping

A (N.O.)

B (N.C.)

Water

inlet

FIGURE 14 - Water

Connections including

Optional Drain and Fill

Kit

Instructions for Installing Optional Fill & Drain Kit

NOTE: Follow this part of the instructions included in the valve pack-

ages for attaching valves to the water line only. The remainder of the

instructions with the valves do not apply to this type of application.

Water Line Connections (See illustration)

Supply (3-Way Valve) Connections - connect

the water supply line to

"B" (normally closed).

Connect the water drain line to

"A" (normally

open). Connect the middle outlet to supply

the water to the cooling module reservoir.

Drain (2-Way Valve) Connections - Connect

the drain pipe from the reservoir to

"A". Con-

nect the outlet side to

"B" and connect into

drain lines from the cooling reservoir and the

supply valve.

WARNING: Risk of electrical

shock. Disconnect the power.

Electrical Connection (requires black and

white 14-gauge wires) - Refer to furnace

wiring diagram:

1. Refer to the wiring diagram for terminal connections (NOTE: If kit is not ordered with the system, connections will not be

shown on the diagram. Terminal connections are specific to each system. Contact the factory for terminal connections. Be

prepared to provide all model information.)

2. Run field-supplied black wire from the electrical compartment (terminal on the wiring diagram) of the evaporative cooling

module and connect to the black wire on both the 3-way and the 2-way valve.

3. Run field-supplied white wire from the electrical compartment (terminal on the wiring diagram) of the evaporative cooling

module and connect to the white wire on both the 3-way and the 2-way valve.

6.0 Mechanical

(cont'd)

6.2 Unit Inlet Air

(cont'd)

6.2.4 Evaporative

Cooling Module -

Options AS4 and AS8

(cont'd)

All Cooling Modules - A manual water shutoff should be installed upstream of the

inlet, at a convenient non-freezing location, to allow the water supply to be turned on

and off. If necessary, install a bleed line between the manual valve and the cooling

module inlet to allow drainage of the line between the shutoff valve and the cooling

module.

All cooling modules are equipped with an overflow and drain fitting. The fittings are

in the cabinet bottom and come complete with a locknut and a sealing gasket. Check

these fittings for tightness before installing the overflow and drain piping. The drain and

overflow fitting will accommodate a 3/4" garden hose thread and is tapped with a 1/2"

female pipe thread for iron pipe.

An optional automatic fill and drain kit (Option CT1) is available that will automatically

release supply water to the cooling module when a call for cooling is made and will

drain all water from the reservoir when the cooling switch is deactivated or a cooling

thermostat is satisfied. See

FIGURE 14. If installing an optional fill and drain kit, follow

the instructions. Consult the wiring diagram for electrical connections.