Triner Scale TS60KD-1010 User Manual

Page 3

Advertising
background image

Assembly

Guide Triner

TS60KD-1010

Platform

Scale

3

3.

Place the first weighing deck into position.
Using a forklift, move the first weighing deck into position.

Before lowering the deck to the ground:

a. Remove the access panel to the junction box compartment and feed the cable

out the hole in the bottom of the compartment. Replace and secure panel.
Place the bundled cable on top of the weighing deck.

b. Place a retaining plate under each of the four feet, being sure to position the

two mounting holes outside the deck.

c. Carefully lower the deck to the ground.
d. Adjust the four leveling feet so that the scale is not “rocking” corner to corner.

There should be even pressure on all four leveling feet against the concrete. If
required, further adjust the feet so that the scale platform is close to being even
with the edge of the ramp.

FIGURE 2: Position the first weighing deck, place the retainer plates and feed out the cable.

Advertising