A. VALVE ASSEMBLY –

1

/

2

" &

3

/

4

" G4 MARATHON, G4R MARATHON

Flow Control Division

Section 1.0

14. Apply thread locking compound to the threads of the

top cap fasteners. Tighten the four top cap fasteners to
7 ft-lbs using a torque wrench. Reference Torque Table
#1a & 1b on page 12.

15. Loosen the adjuster fasteners to approximately

3

/

16

"

above adjuster. Then rotate the valve plug back and forth
3 times, making it rise upward.

16. Retighten adjuster fasteners to a torque of 10 to 12 in-lbs.

or until the height of the plug port is positioned approxi-
mately

1

/

16

" above to flush with the body port, whichever

occurs first.

17. Rotate plug back and forth a couple times to make sure

the stops and ports line up properly. The final assembled
valve should look similar to Figure V A-10.

18. LEAK TESTING: Anytime a valve has been modified in

any manner, including fastener changes, it should be
retested. Normal testing using gas, should be at 150 PSI
for Class 150 and 300 PSI for Class 300 valves from
1/2" through 6". It should be noted, however, that this
test does not meet the requirements of ANSI, API, or
MSS. For test procedures complying with these specifi-
cations, refer to the appropriate published specification
or contact Flowserve.

FIGURE V A-10
ASSEMBLED VALVE

ADJUSTER FASTENER

ADJUSTER

TOP CAP
FASTENER

TOP CAP

BODY

TEFLON BACK-UP
RINGS (2)

O-RINGS (2)

PLUG

STOP COLLAR
RETAINER

STOP COLLAR

GROUNDING

SPRING

THRUST

COLLAR

DIAPHRAGM

SLEEVE