Page 15

SECTION 2.0: NETWORK TROUBLESHOOTING TIPS

2.1 TROUBLESHOOTING

NOTE: Also refer to the COMMISSIONING GUIDE located on the preceding pages.

REPORTED PROBLEM

POSSIBLE SOLUTIONS

For turbine meters -

No Flow Signal (while

hydronic system is

active)

• Verify 24 VDC supply voltage to the flow meter.

• For insertion meters, verify the flow meter is correctly inserted

into the pipe (using depth gage).

• For insertion meters, verify that the flow meter electronics

enclosure is parallel with the pipe.

• Verify correct wiring to the flow meter (see wiring diagram).

• For turbine meters, check turbine(s) for clogging due to debris.

• If none of the above, check hydronic system to ensure that flow is

really present in the line.

• NOTE: Flow meter function cannot be verified by blowing on the

turbine(s). The sensing system requires a conductive liquid to

operate. You can test it by swirling it around in a bucket of water

and looking for the flow indicator LED to flash at the D-100.

Displayed flow rate too high
or too low

• Verify pipe size. Contact ONICON if pipe size is different from

calibration tag.

• For insertion meters, verify that meter is inserted correctly into the

pipe (using depth gage).

• For insertion meters, verify that the flow meter electronics

enclosure is parallel with the pipe.

• For dual turbine meters, confirm that both turbines produce

pulses.

• For turbine meters, check turbine(s) for debris.

• Verify supply voltages (to display and flow meter).

Device is not communicating
with the Lon Talk network.

• What is the state of the service pin LED?

• Is it flashing? A flashing service pin LED indicates that the Lon

module has not been commissioned.

• Is it off? A service pin LED that is off indicates that the Lon

module is commissioned and operating normally.

Communications with the
Lon Talk network is inter-
mittent.

• Is the network properly terminated? The Lon TP/FT bus can be

terminated in 2 different ways.

• A single RC filter can installed at any point on a free topology

network. A dual termination scheme is used with 2 RC filters

installed at the ends of bus networks. Refer to the drawings below

for details.

• What type of cable is used to wire the network? TP/FT networks

should only use twisted shielded pair cable. (Belden 85102 or

equiv.)

For technical assistance, contact ONICON Incorporated at (727) 447-6140.