greater than 1200°F (650°C), but less than 3000°F (1650°C) in a slightly positive pressure

situation to prevent air in-leakage.

The sensor cannot be exposed in an area with excessive turbulence or high gas velocity,

especially when there is particulate in the atmosphere. In order to comply with these

requirements, SSI recommends that, for glass tanks with regenerative heating, the sensor be

installed vertically in the center of the regenerator crown or horizontally on the regenerator

“target” wall. Please note that target wall life will be significantly less when compared with a

vertical, crown installation.

For glass tanks with recuperative heating, SSI recommends installation in a vertical position in

the flue gas collector, behind the branch off, but in front of the gate valve. Please remember

the temperature constraints when looking for this location.

You must drill 2 ¾ to 3 inch (19.05 to 76.2 mm) holes through the refractory brick. This will allow

easy installation and removal of the SuperOX

TM

Sensor.

Vertical installation

Sensor should be recessed 1 to 2 inches (25.4 to 50.8 mm) into the refractory away from furnace

atmosphere. When installing the probe, it is best to insure this length of insertion. From the hot

face, one will recess the sensor until the readings begin to change. Once a change has been

observed, lower the sensor approximately ½ inch (12.7 mm) and secure the sensor in place.

Horizontal Installation

SSI recommends that the “hot” end of the sensor extend approximately 3 to 5 ½ inches (76.2 to

139.7 mm) beyond the hot face of the refractory. If there is an excessive amount of batch carry-

over, or if the gas stream has a very high velocity, it is recommended that the sensor be

recessed. Batch carry-over and high velocity gas will erode the sensor and significantly reduce

life.

Sensor Preparation before installation

When using the SSI oxygen mounting assembly, place the sensor at the maximum height

possible and lower it toward the furnace 2 to 4 inches (50.8 to 101.6 mm) every five minutes. If

you do not have an SSI Mounting Assembly, note that approximately 2 hours before installing

the sensor, you should lay the sensor on top of the regenerator (for pre-warming), taking care

to protect the sensor head and wiring assembly.

Sensor installation (insertion) rate

WARNING: You must follow operational safety guidelines when drilling, and installing a sensor

in an operating glass furnace. It may be possible to use existing furnace openings. When

repairing a furnace, or planning for new construction, you should consider drilling the holes for

oxygen sensors.

Insertion of the sensor should be no greater than 4 inches (101.6 mm) every 5 minutes.