9.

Complete the Start-Up Data Sheet (Technote 101). The Start-Up Data Sheet and
the Daily Log Sheet (Technote 106) are invaluable in diagnosing the performance
of the equipment, and must be be kept for reference. If you have questions con-
cerning the operation of your machine or the method of data recording, contact
your distributor or the manufacturer.

Figure 2.1

Flow Control Center

CAUTION:

Once the machine is running, with orifices, adjust pressures and
flows to the correct measure, flush machine to drain for
30 - 45 minutes.

CAUTION:

The E2/EZ2-Series machines are designed to run at 50% recov-
ery. To confirm flows are correct, check Table 2.4 (Flow
Specifications for E2/EZ2-Series Machines). To correct any
temperature variations, check Table 2.4. If your E2/EZ2-Series
machine is operating under permeate back pressure to point of
use, refer to Table 2.5 (E2/EZ2-Series Permeate Back Pressure
Correction Factors).

CAUTION:

Machine performance is based on a feed water temperature of
77°F (25°C). If feed water temperature is other than
77°F (25°C), reference Table 2.4 (Temperature Correction
Factors) to confirm machine’s performance