3.1 FUNCTIONAL

TESTS

AND

ADJUSTMENTS

Following transfer switch installation and interconnec-

tion, inspect the entire installation carefully. A compe-

tent, qualified electrician should make the inspection.
The installation should comply strictly with all applica-

ble codes, standards, laws and regulations. All electri-

cal connections must be correct and in compliance with

applicable codes and standards.
Make sure the standby generator is ready. This

includes checking engine oil level, coolant level, fuel

supply, batteries and other items specified in the

Owner’s Manual for specific generators.
Complete all functional tests as outlined in the Post

Installation Start-Up Adjustments section. Do this

before placing the transfer switch into service.
Functional tests of the transfer switch include these

tests: (a) Manual Operation, (b) Voltage Checks and (c)

Electric Operation.

To avoid damaging the transfer switch, perform
functional test in the exact order given.

Before proceeding with functional tests, read and be

sure you understand all instructions in this section.

Also, read the instructions and information on tags and

decals affixed to the transfer switch. Note any options

and accessories that might be installed or provided with

the switch and review their operation.

Do not attempt manual operation of the transfer
switch until after all power voltage supplies to
the switch have been turned off. Failure to turn
off power voltage supplies may result in danger-
ous and possibly fatal electrical shock.

3.2 MANUAL

OPERATION

Instructions for “V” type transfer switches: Test manu-

al operation as follows:
1. Check that the generator’s Auto-Off-Manual switch

has been set to the OFF position.

2. Turn Off the UTILITY power supply to the transfer

switch, using whatever means provided (such as the

UTILITY source main line circuit breaker).

3. Set the generator’s main circuit breaker to its Off or

OPEN position.

Failure to turn OFF all power voltage supplies to
the transfer switch before attempting manual
operation results in extremely hazardous and pos-
sibly fatal electrical shock.

4. Remove the manual transfer handle from the enclo-

sure.

5. Place open slot of the manual transfer handle on the

small tab of the transfer switch operating lever

(Figure 3.1).

6. Pull manual transfer handle downward. If handle is

down, LOAD is connected to STANDBY power

source. If handle is up, LOAD is connected to UTIL-

ITY power.

7. Move the transfer switch main contact to both posi-

tions several times. Leave the transfer switch in the

UTILITY position and connect LOAD to the UTILITY

power source (manual operation lever is up).

Figure 3.1 — Transfer Switch Operation (“V” Type)

DANGER

DANGER

!

Section 3 — Post Installation Start-Up Adjustments

Generac 100 Amp Transfer Switch

Advertising
This manual is related to the following products: