3.3 TRANSFER

SWITCH

VOLTAGE

CHECKS

1. Turn ON the UTILITY power supply to the transfer

switch with whatever means provided (such as the

UTILITY main line circuit breaker).

Proceed with caution. The transfer switch is now
electrically hot. Contact with live terminals
results in extremely hazardous and possibly fatal
electrical shock.

2. With an accurate AC voltmeter, check for correct

voltage across terminal lugs N1 and N2; N1 to NEU-

TRAL; and, finally, N2 to NEUTRAL (see Wiring

Diagram on Page 8).

3. When certain that UTILITY supply voltage is correct

and compatible with transfer switch ratings, turn

OFF the UTILITY supply to the transfer switch.

4. On the generator panel, set the Auto-Off-Manual

switch to MANUAL position. The generator should

crank and start.

5. Let the generator stabilize and warm up at no-load

for at least five minutes.

6. Set the generator’s main circuit breaker (CB1) to its

ON or CLOSED position.

Proceed with caution. Generator output voltage
is now being delivered to transfer switch termi-
nals. Contact with live terminals results in
extremely dangerous and possibly fatal electrical
shock.

7. With an accurate AC voltmeter and frequency meter,

check the no-load, voltage and frequency meter at

transfer switch terminal lugs E1, E2 and NEUTRAL.

Readings should be as follows:
a. Frequency................................61-63 Hz
b. Terminals E1 and E2 ..............242-253 volts
c. Terminal E1 to Neutral ..........121-126 volts
d. Terminal E2 to Neutral ..........121-126 volts

8. Set the generator’s main circuit breaker (CB1) to its

OFF or OPEN position.

9. To shut down the generator, set its Auto-Off-Manual

switch to its OFF position.

NOTE:

Do NOT proceed until generator AC output voltage

and frequency are correct and within stated lim-

its. If the no-load voltage is correct but no-load

frequency is incorrect, the engine governed speed

probably requires adjustment. If no-load frequen-

cy is correct but voltage is not, the voltage regu-

lator may require adjustment.

3.4 GENERATOR TESTS UNDER LOAD

1. Set the generator’s main circuit breaker to its OFF

or OPEN position.

2. Turn OFF utility power to the transfer switch.
3. Manually move the transfer switch main contacts to

their STANDBY position.

4. To start the generator, set the Auto-Off-Manual

switch to MANUAL. When engine starts, let it stabi-

lize for a few minutes.

5. Turn the generator’s main circuit breaker to its ON

or CLOSED position. The generator now powers all

LOAD circuits. Check generator operation under

load as follows:

• Turn ON electrical loads to the full rated

wattage/amperage capacity of the generator. DO

NOT OVERLOAD.

• With maximum rated load applied, check voltage

and frequency across transfer switch terminals E1

and E2. Voltage should be greater than 230 volts;

frequency should be greater than 58 Hz.

• Let the generator run under rated load for at least

30 minutes. With the unit running, listen for

unusual noises, vibration, overheating, etc., that

might indicate a problem.

6. When checkout under load is complete, set the gen-

erator’s main circuit breaker to its OFF or OPEN

position.

7. Let the generator run at no-load for several minutes.

Then, shut down by setting the Auto-Off-Manual

switch to its OFF position.

8. With the manual transfer handle, move the switch’s

main contacts back to their utility position, i.e., load

connected to utility power supply. The handle and

operating lever of the transfer switch should be in

the up position.

9. Turn on the utility power supply to the transfer

switch, using whatever means provided (such as a

utility main line circuit breaker). The utility power

source now powers the loads.

10. Set the generator’s main circuit breaker to its ON or

CLOSED position.

11. Set the generator’s Auto-Off-Manual switch to its

AUTO position. The system is now set for fully

automatic operation.