Installation, 3 installation – ICI - Innovative Creations, Inc. AX User Manual
Page 10
 
INSTALLATION
8
3 INSTALLATION
3.1 SITING
Our steam boilers are supplied as units and do not need any foundation work. A flat even floor only is 
needed, that can be raised by 5-10 cm. 
3.2 WATER
CONNECTIONS
The steam boilers once positioned are connected to the system as follows (Fig. 9): 
Water 
From the condensate collection tank (10) (if existing; otherwise from the treated water tank) to the suction 
side of the feed water pump (9). 
Steam 
From the main steam take-off valve (3) to the user services (distributor or others), from the safety valve 
outlets (6) to outside the boiler room in a safe position. 
Drains 
From the level indicator drains (16), the boiler drain (17) to the drainage network. 
Fuel 
Connection to the burner foreseen for fuel oil or natural gas. 
Fig. 9 – System diagram
LEGEND 
1. Boiler 
2. Smokestack 
3. Steam 
take-off
4. Burner 
5. Pressure 
switches
6. Safety valves 
7. Condensate 
return
8. Electric pump supply 
9. Feed water pumps 
10. Condensate collection tank 
11. Water level 
12. Water treatment 
13. Water supply 
14. Breather 
15. Condensate tank drain 
16. Level indicator drain 
17. Boiler drain 
18. Safety valve drain 
19. Example of user service