Gate Operator Installation Checklist

1 . The gate has been checked to make sure it is level and moves freely in both directions .

2 . Potential pinch areas have been guarded so as to be inaccessible

OR have

contact and/or non-contact obstruction sensing devices installed .

3 . The installer has installed one or more contact or non-contact obstruction sensing

devices, in compliance with UL325 requirements for this installation .

4 . If pedestrian traffic is expected, a separate pedestrian gate has been

installed, a minimum of seven feet from the gate . The customer has been
informed that all pedestrian traffic must use the pedestrian gate .

5 . Warning signs have been installed on each side of the gate in highly visible locations .

The customer has been informed that these signs must remain at all times .

6 . There are no controls installed on the gate operator, or within seven feet of the gate .

7 . The installer has properly adjusted the obstruction sensing feature and has tested

the gate to make sure that the gate stops and reverses a short distance with minimal
resistance applied (40 lbs . on a swing gate at the end of the gate, 75 lbs . on a slide gate)

8 . The installer has instructed the customer in the proper use of the gate operator and reviewed

all of the operational functions, obstruction sensing devices, warning beeper and reset, etc .

9 . The installer has instructed the customer in the proper use of the operator’s

manual disconnect feature . The manual disconnect must never be used
while the gate is in motion . The power switch must be turned off before
using the manual disconnect and disengaging the operator .

10 . The installer has reviewed all safety instructions with the customer, and has left

the safety instructions and owner’s information sheets for their reference .

11 . The installer has answered any questions the customer has regarding the

operation of the gate operator and gate operator safety precautions .

12 . The installer has explained to the customer that a regular maintenance

schedule for both the gate and the gate operator is recommended .

By signing this installation checklist, I/we hereby certify that each item listed and checked above has been covered by the
installer and is clearly understood by the customer .