Task 014: Testing the BitStorm 1900 Installation

Testing a BitStorm 1900 installation includes the following tasks:

•

Testing voice connectivity

•

Testing data connectivity

•

End-to-end connectivity

The following sections contain testing-related information followed by
the BitStorm 1900 testing tasks. Testing tasks for network support
equipment such as LAN/WAN routers are not included in this
document.

BitStorm 1900 Testing Locations

Primary test points for installation include the following:

•

Customer premises cross-connect containing the connections for
the BitStorm 1900 and customer premises equipment

•

Modem user locations

If the system is having trouble, other test points may be required.

Step

Procedure

1.)

Review the BitStorm 1900 Test Point Diagrams as follows:

• Figure 2-21, "Voice/Data System Test Points," on page 97

shows the schematic layout and primary test points of a
BitStorm 1900 voice/data system.

• Figure 2-22, "Data-only System Test Points," on page 98 shows

the schematic layout and primary test points of a BitStorm 1900
data-only system.