Rancilio S20 User Manual

Page 89

Advertising
background image

89

Cleaning the filters and delivery heads

Operation to be carried out when the machine
is off and cold.

● Prepare a solution of 4 sachets of detergent

powder Code 69000124 dissolved in a litre of
boiling water in a stainless steel, plastic or glass
container (NOT ALUMINIUM OR IRON).

● Remove the filters and immerse them with the filter

holders in the prepared solution, leaving them for
at least 20/30 minutes (all night is better).

● Remove them from the container and rinse them

thoroughly in running water.

● Remove the cup rack 1 (Fig.13), slide out the drip

tray and clean them both.

Models SYSTEM CD -LE

Operation to be carried out while there is still
some pressure in the machine.

● Drain the water from the boiler (approx. four litres)

using the hot water tap 7;

● Wait for the machine to te-establish its correct

thermal balance before use.

Models S27 - MIDI DE - SYSETM DE

Operations to be carried out with the machine
operative and under pressure.

Prepare a container that can hold at least two litres
od water (four litres dor model System) and place it
unter the hot water spout.

● Hold down the delivery button 8 for at least four

second. When this button is released, the machine
will deliver water continuously

● After two litres have been drawn off (four litres for

the model System), press the delivery button again
to stop dispensing.

● Wait for the machine to re-establish its correct

thermal balance before use.

Fig. 13

Fig. 14

● Check and clean the drainage pump 1 (Fig.13),

removing any sludge with the help of a spoon.

10.3. Periodical maintenance

Models TECNA CD - TECNA DE

Have been fitted with economizers which do not draw
water from the boiler to make hot water, the water in
the boiler need only to be renewed from time to time.

10.3.1. Renewal of water in the boiler

Models MIDI - TECNA

To be carried out only by qualified personnel.

● Turn off the machine and wait for the pressure in

the boiler to diminish (gauge needl on “0”).

● Using a spanner firmly hold 1 the outlet pipe 2

Fig.14 situated about the drainage sump while
loosening the hexagonal sealing screw 3 by 3 turns
at the most.

● Drain off the water and tighten the screw 3.
● Refill the boiler (paragraph 7.3.).

Advertising
This manual is related to the following products:

S24, S26, S27