Chapter 2. installation and setup, Site requirements and prerequisites, Power – RAD Data comm ASMi-31 User Manual

Page 21: Ambient requirements, Chapter 2 installation and setup

Advertising
background image

16-05-01 13:37

Site Requirements and Prerequisites

2-1

Chapter 2
Installation and Setup

This chapter provides the following information for the ASMi-31 standalone
model:

•

Site requirements and prerequisites

•

Package contents

•

Instructions for mechanical installation

•

Instructions for electrical installation.

After installing the unit, refer to Chapter 3 to assure normal operation.
In case a problem encountered, refer to Chapter 4 for test and diagnostic
instructions.
Refer to Chapter 5 for additional information on the ASMi-31/R card
version.

2.1 Site Requirements and Prerequisites

Power

AC-powered ASMi-31 units should be installed within 1.5m (5 ft) of an
easily accessible grounded AC outlet. The outlet should furnish 115 VAC or
230 VAC.

DC-powered ASMi-31 units require -48 VDC power source, which must be
adequately isolated from the mains supply.

•

Allow at least 90 cm (36 in) of clearance at the front for operating and
maintenance accessibility.

•

Allow at least 10 cm (4 in) clearance at the rear of the unit for signal lines
and interface cables.

Ambient
Requirements

The ambient operating temperature of ASMi-31 is 0 to 50°C (32 to 122°F)
at relative humidity of 90%, non-condensing.

Order from: Cutter Networks

Ph:727-398-5252/Fax:727-397-9610

www.bestdatasource.com

Advertising