HOO D W IDTH

DIM. "W " DIM. "K "

DIM. "Z"

30"

29 - 1/8"

2 - 1/2"

7 - 1/16"

36"

35 - 1/16" 2 - 1/2"

7 - 1/16"

Table 3

Side slot x 4

Figure 4b

Figure 4a

9

Wall Mount Installation

Note: see below if cabinet installation is preferred
3. After the hood installation height has been

determined draw a horizontal line at a distance
above the cooktop equal to the desired hood
installation height plus 7- 1/2”. See also Figure 4a.

4. Find the centerline of the cooktop. Draw a

vertical line along this centerline up to the hori-
zontal line drawn in step 1 and draw a vertical
line right and left at a distance of12-5/8” to
determine the mounting locationof the
mounting hooks shipped with the hood.

5. Fit two mounting hooks on the wall to hang the

hood through the provided slots (2 wall
anchors + 2 hooks + 2 screws 5x35).

6. Run 10” Duct, long enough to reach the

transition once the hood has been installed plus
1 1/2” inch to connect ductwork. Fix Duct to
transition with screws and seal withtape.

7. Remove 1 of 2 knockouts and install 1/2”

conduit connector in j-box.

8. Hang the hood and adjust its position through

the screws on the hooks.

9. Fix the hood to 4 additional point, 2 on

upperside, 2 on lower side (use 4 wall anchors
+ 4washers + 4 screws 5x35.

Cabinet Installation:

Note: See above if wall mount installation is preferred
Note: Distances on Table 3.3
.
Find the centerline of the cabinet bottom. Draw a line
along this centerline from rear to front of the cabinet.
See also Figure 4b.

4. Draw two lines, one at a K distance from thewall,

the other one at a Z distance from theprevious line.
Mark 4 points, two along each line at a distance of
half W from the center line, to determine the screw
locations.

5. Fit 4 screws on cabinet bottom do not tighten

completely but leave a space of about 1/2” from
cabinet bottom surface and head screws.

6. Run 10” Duct, long enough to reach the transition

once the hood has been installed plus1 1/2” inch for
connect ductwork.

7. Remove 1 of 2 knockouts and install 1/2”conduit

connector in j-box.

8. Hang the hood on screws through side slots provided

on hood top.Tighten the four screws. Note: If possible
fix the hood on the wall at 4 additional point (2 on
upper side, 2 on lowerside).

9. From the inside of the cabinet attach the transition

on upper outlet.

Center Hole