Step 4 electrical connections for model 585, Step 5 electrical connections for model 580, Step 6 testing of pump operation – Zoeller AQUANOT 585 User Manual

Page 5: Step 3 installation of the discharge piping

Advertising
background image

5

BATTERY

RED LEAD

TO POSITIVE(+)

TO NEGATIVE(-)

BLACK LEAD

SWITCH

CUT AWAY OF SUMP PIT

RED LEAD

TO POSITIVE(+)

MOTOR

CHARGER

NEGATIVE(-)
BATTERY TERMINAL

BATTERY TERMINAL

POSITIVE(+)

OUTLET

ALARM

BLACK LEAD
TO NEGATIVE (-)

© Copyright 2009 Zoeller Co. All rights reserved.

STEP

4

Electrical Connections for Model 585

Note: This Step is for the

Aquanot

®

II (Model 585). Proceed to STEP 5

for installation of

Aquanot

®

I (Mod el 580).

4.1) Complete electrical connections as shown in Fig ure 4.1.

4.2) Proceed to STEP 6.

Do not place battery or charger directly on ground. If the

battery or charger must be placed directly on the ground, then place a
piece of wood between the units and the ground. Do not put the charger
on top of the battery.

Figure 4.1

STEP

5

Electrical Connections for Model 580

5.1) Complete the electrical connections as shown in Figure 5.1.

Do not place battery or monitor directly on ground. If

the battery or monitor must be placed directly on the ground, then
place a piece of wood between the units and the ground. Do not
put the battery monitor on top of the battery.

Figure 5.1

STEP

6

Testing of Pump Operation

6.1) Unplug the primary pump so that it does not start.
6.2) Fill pit with water until the

Aquanot

®

starts.

6.3) Verify that the pump starts and stops at the desired on/off points.
6.4) Verify that there are no leaks in the discharge line.
6.5) If adjustment is necessary, raise or lower the appropriate stop(s) according to STEP 2.

IMPORTANT: Spacing between upper and lower stops determine amount of water removed from pit.

6.6) If the pump is not operating properly after following the above steps, refer to the Troubleshooting guide on page 8.
6.7) When

fi nished testing plug primary pump back into AC receptacle.

STEP

3

Installation of the Discharge Piping

3.1) Assemble the discharge pipe into the pump as shown in Figure 3.1.

IMPORTANT: In order for this installation to work properly, a check valve

must be installed onto the discharge line.

P/N

30-0100

P/N

30-0101

P/N

30-0102

P/N

30-0103

Figure 3.1

SK1784

SK1783

SK1778

Recommend the following Zoeller check valves:
Some local codes require union check with ball valve.

}

PRIMARY PUMP

DISCHARGE

MAIN

CHECK VALVE

LINE

PRIMARY PUMP

CHECK VALVE

DISCHARGE

LINE

MAIN

OR