Installation procedure – Banks Power Dodge Trucks: (Diesel ’98 - 02 5.9L Cummins ISB) Speed Control- Banks SmartLock (used with CBC-equipped Banks Brake) User Manual
Page 5
Figure 3
Figure 4
CAuTioN: installation of
the SmartLock Trans Brake
is NoT complete until
Functional Testing,
described on pg. 7 of
this manual, has been
successfully completed.
PNEumATiC LiNE
PRESSuRE BooST
ACTuAToR ASSEmBLY
iNSTALLATioN:
NOTE: The following
instructions assume that a
Banks Brake system has been
previously installed on the
vehicle.
1.
As a precaution,
disconnect the ground of the
battery. If there is more than
one battery, disconnect both.
2.
Raise and support the
vehicle.
3.
Disconnect the cable from
the kick-down lever on the
side of the transmission case
as shown in Figure 1.
4.
Disconnect the return
spring attached to the kick-
down lever as shown in
Figure 2. Save the spring for
reuse later.
5.
Loosen the tightening
screw and remove the OEM
kick-down lever as shown in
Figure 3.
6.
Remove the bolt shown
in Figure 4 from the
transmission case and install
the line pressure boost
actuator bracket as shown.
Temporarily finger-tighten the
bolt to allow adjustment.
7.
Slide the actuator control
lever over the throttle valve
shaft and tighten the bolt.
Re-attach the return spring
to the transmission case