Recommended tools for installing vtdl-72-8x9 door – Grain Systems Bin Accessories PNEG-1336D User Manual

Page 16

Advertising
background image

16

PNEG-1336D VTDL-72-8X9D - VTDL-78-8X9D Door

4. Assembly Instructions

15. Assemble outer cover as shown

on Page 27

. Apply strip of caulk behind column and header angles

before attaching them to column and header beam clips. Attach center post and center door latch
(VTDL-0293) to header angle and threshold weldment. Apply caulking to the top and bottom of
center post. Assemble door outer cover, reinforcement channels, hinges, latch brackets and door
handles as shown

on Page 27

. 3/8" x 1" Bin bolts will be used for all connections. Use 3/8" nut and

sealing washer as spacer between latch bracket and outer cover. Place outer cover in doorframe
and align hinge weldment (VTDL-0337) with hinge bracket (VTDL-0292). Insert hinge pins
(VTDL-0335) through hinges and hold in place with washers and cotter pins. Review details
G-I

on Page 28

for connection details. Adjust door hinges and latches as necessary until door

opens and closes smoothly. Apply foam seal strip around perimeter of outer cover and caulk as
necessary to seal outer cover. Place decals DC-GBC-2A and DC-GBC-2S on the outer cover as
shown

on Page 28

.

16. To open door, open outer cover and remove door cover or tie back to bin, remove center post,

unbolt door panels from doorframe. Do not remove hinges or unbolt door panels from one another.
Swing door panels open to remove center column. Provisions should be made to hold the door
panels open while center column is being removed and bin is being cleaned. Unbolt top of center
column from header beam and remove shim plate. Slide center column section inside off the
threshold weldment, tilt outward and remove. Caution center column is extremely heavy and proper
equipment should be used for removal. Temporary ramps should be made to avoid driving over the
door panel attachment plates of the threshold weldment. Once the bin is fully emptied, re-install the
center column section, close door panels, and bolt panels to doorframe. It may be necessary to
re-seal around door panels and column weldments. Close outer cover and re-seal as necessary.
Inspect all decals each time door is opened and replace if damaged or missing.

Recommended Tools for Installing VTDL-72-8X9 Door

1. Forklift or similar piece of equipment capable of lifting 1500 lbs. at heights above 10'.

2. Welder

3. Plasma cutter, torch, or similar tool for cutting base plates.

4. Concrete drill for installing 3/4" epoxy type anchors (if anchors are used).

5. 1/2" and 7/16" drill bits.

6. Sockets and wrenches including 9/16", 5/8", 1-1/8", and 1-1/2" sizes.

7. Drift pins and/or pry bars.

Advertising