HR Unloader Restrictor Adjustment

Inspection/Clean-Out Plate Installation

Once the installation of the auger tubes and auger is complete, insert the inspection/clean-out plate
or the optional unloader switch.

The inspection/clean-out plate is to be installed per the following instructions

(See Figure 6)

:

1. Back off both wing nuts to the stud ends.

2. Slide the plate onto the lower side of the unloader opening.

3. Move the plate first against the side of the unloader then upward toward the top of the unloader.

4. Tighten the wing nuts while holding the plate steady.

Figure 6 Clean-Out Plate Installation